BACKGROUND
National Grid needed to provide a new Minimal Offtake Connection (MOC) into the National Transmission System (NTS) in Stockton-on-Tees, Middlesborough for client Statera Energy.
Statera Energy, a leading UK developer of flexible energy generation and storage technologies, required a new gas connection to supply their two new gas-fired peaking plants on land adjacent to the A1185, East of Cowpen, Bewley.
The new Saltholme North and South Power Stations will play a valuable role in the future UK energy system by providing flexible delivery of electricity to the grid to cover shortfalls and increases in demand.
Each site comprises of four gas fired reciprocating engines with a capacity of 50MW. Both can reach full output capacity in 5-10 minutes providing sustained delivery of electricity to the grid in times of high demand.
To meet this requirement, National Grid proposed to construct a new MOC, adjacent to the existing Feeder 6 high-pressure Pipeline which is located in close proximity to the Power Stations.
The MOC facility was constructed on newly flattened ground, as part of a larger construction project and will have a footprint of around 25m x 25m, excluding planting.

An adjacent compound would house a new Pressure Reduction Station (PRS) within the overall site boundary, this was owned and maintained by Statera Energy.

SCOPE
National Grid appointed Rayden Engineering Ltd (REL) as the Principal Contractor to construct two new Minimum Offtake Connections (MOC) adjacent to the existing Feeder 6 Pipeline.
The project was successfully completed under no-outage conditions in accordance with CDM 2015 regulations. REL was responsible for fabrication, mechanical, and installation works, along with all associated civil and temporary works (TW).
Project scope consisted of the following:
- 150mm (6”) Hot Tap connection from existing 900mm (36”) Feeder 6 Pipeline.
- Inlet pipework from Feeder 6 to Saltholme Power Station MOC facility.
- 150mm (6”) manual block valve & bypass arrangement to facilitate maintenance without interruption to Statera (customer) supply.
- Outlet pipework from MOC for Statera to connect to Above Ground Installation (AGI).
- Telemetry system & housing for remote transfer of site information.
- Insulation joints (IJ) to electrically isolate NG pipework from Statera.
- Supply & installation of Cathodic Protection System.
- Testing, Pre-commissioning & Assistance with Commissioning.



SERVICES DELIVERED
All work was delivered in accordance with IGE/TD/1 Edition 5 and NG specifications T/SP/PW/11 Parts 1 & 2 and T/SP/SSW/22. This included:Project Management:
- Dedicated Project Management team established with key REL staff.
- Planning, management & operation for: Construction Programme, Quality Assurance, Environmental, Health & Safety, Risk Assessments (HAZON) & Method Statements (RAMS), Weld Procedure Specifications, Temporary Works Design (TW), Procurement, Emergency Response, Waste Management, Traffic Management & Security Plans.
- Coordination of work between contractors to ensure cooperation.
Offsite Fabrication:
- To minimise on-site time, REL fabricated some pipework offsite at our head office Workshop:
- Fabrication of pipework headers & spools.
- Fabrication of 150mm inlet & outlet pipework.
- 100% inspection, Non-Destructive Testing (NDT) using Phased Array Ultrasonic Testing (PAUT) to T/SP/NDT/2.
- Paint & hydrostatic testing & drying all pipework.
- Cleaned & prepared pipework for transportation to site for installation.
Construction Works:
- Survey, set out site – working area, placed hardcore & compound fencing.
- Provision & set up temporary site facilities for welfare, storage, signage, plant etc.
- Concreted bases for pipe supports, Control Room, Pressure Transmitters & Satellite.
- Excavated & caste concrete bases for Insulation Joints (IJ).
- Excavated & lay ducting & draw pits for E&I Works.
- E&I installation completed by others.
Grouted Tee Installation:
- Trial holes to determine location of Feeder 6 live pipeline.
- Excavation of Grout Tee/Drill pit to T/PM/SSW2.
- Construction of concrete base with access for Tee/Drill pit
- Removal of pipe coating, visual & dimensional checks.
- Offtake point formed below ground on the existing 900mm Feeder 6 pipeline with 150mm branch connection with single UPT / 150mm full bore construction valve which was encapsulated before backfilling.
- Assisted specialist contractor fitting 900x150x150mm grouted reducing Tee, 150mm flanged valve & testing.
- Coating of Tee & Valve.
- Fitted Tee/Pipe supports next to Grouted Tee.
- Assisted with specialist Under Pressure Drilling, withdrawing drill & blanking off.
- All work to T/PR/P/19 ‘Procedure for the installation of grouted tees on transmission pipelines in service.’

Temporary Access Pit to Feeder 6 Pipeline






Pipework Installation:
- All prefabricated pipework delivered to site by REL Haulage team.
- Fitted & bolted Above Ground pipework spools on concrete supports.
- Excavation of pipework inlet trench, lower lay, completed connecting welds, Non-Destructive Testing (NDT) using PAUT & lift out for drilling.
- Excavation of pipework outlet trench, lower lay, completed connecting Welds, NDT using PAUT & coating.
- All welded joints to T/SP/P2 & T/SP/P8, /SP/P/9, T/PR/P/19.
- 100% inspection of all pipework & NDT to T/SP/NDT/2.
- Outlet pipework to AGI installed with blanked end with captive vent plug to allow Statera to connect safely.
- Repositioned Inlet Pipework after drilling & coated.
- Supply & installation of Cathodic Protection System (CP) as per design & test/marker posts.
- MOC pipework was constructed & tested as one pressurised system to IGEM/TD/1 Edition 5 & T/PM/PT/1.
- Hydrostatic testing to 105 bar, water drained & pipework dried to -20oC dew point.
- Bed & surround pipe with fine grain sand, backfill trenches & tee/dril pit to T/PM/SSW/22.
- CP commissioning – DCVG & CIPS surveys.
- Completed RE18 final documentation.
- Provided NGGT assistance with commissioning.
Reinstatement & Completion:
- Security fencing installed to MOC compound perimeter.
- Construction of soakaway pits & drainage.
- New concrete footpath, terram & stone chippings to compound area.
- New tarmac road, kerbing & bollards.
- Full site clearance & demobilisation: removal of cabins, offices & other temporary structures.

150mm Branch Connection from MOC AGI to Feeder 6 Pipeline



OUTCOME
This project was completed successfully, adhering to the programme specifications with no complications. All tasks were finished on schedule, within the allocated budget, and in accordance with the approved design and Risk Assessment and Method Statements (RAMS).
REL fulfilled all their responsibilities under CDM 2015 and provided comprehensive Handover Documentation at the project’s conclusion, including As-Built drawings, the Health & Safety File, and Data Books.
Both Saltholme North and South Power Stations went into full commercial operation in December 2021, successfully supplying over 111K homes each with electricity during peak times of demand.