MEC for Theddlethorpe Gas Terminal Above Ground Installation

Nat Grid logo

BACKGROUND

National Grid needed to provide a new Minimal Entry Connection (MEC) into the National Transmission System (NTS) at their Theddlethorpe Gas Terminal in Mablethorpe, Lincolnshire.

Gas was to be extracted from the nearby Saltfleetby Gas Fields by Onshore Oil and Gas company Angus Energy (AE). This had previously been delivered into the NTS via the ConocoPhillips Terminal, and then to Theddlethorpe Terminal. However, due to industry changes this route was no longer available.

AE needed to produce dry gas from two sites in the Saltfleetby area and proposed to deliver this directly into the NTS at the existing Theddlethorpe delivery facility through a new private pipeline.

AE therefore required a new MEC into the Feeder 17 Hatton / Theddlethorpe NTS pipeline to facilitate the direct delivery of processed gas from the Saltfleetby Gas Field.

Angus Energy Logo

Lifting New 100mm Pipework Assembly at Feeder 17 Connection
Connecting New 100mm MEC Branch to Existing Feeder 17 Pig Trap Bridle
Installing Adjustable Pipe Support to 200mm Bridle Pipework

SCOPE

NGT appointed Rayden Engineering Ltd (REL) as Principal Contractor to carry out all works under CDM 2015. REL was responsible for fabrication, mechanical, and installation works, along with all associated civil and Temporary Works (TW).

Project scope consisted of the following:

  1. New MEC at Theddlethorpe Gas Terminal connected to Feeder 17 (Hatton Theddlethorpe).
  2. 100mm (4”) connection to existing 200mm (8”) Above Ground (AG) bridle pipework of Pig Trap ‘C’ on Feeder 17.
  3. Interconnecting pipework from Feeder 17 bridle connection to Theddlethorpe MEC (Twin Stream Double Block & Bleed – DBB) AG Valve Skid unit.
  4. Outlet pipework from AG Valve Skid unit to Tie-In point (to be connected by AE).
  1. Supply & installation of Cathodic Protection System (CPS).
  2. Testing, pre-commissioning & assistance with commissioning.
  3. Construction of reinforced concrete foundations, pipe support bases & isolation joint supports.
  4. Construction of E&I enabling civils including duct routes, draw pits & compound infrastructure.
Completing New Tie-in at Feeder 17 Bridle
Excavation of 100mm Pipework Trench
Backfilling 100mm Pipework to AG Valve Skid

SERVICES DELIVERED

This project was delivered during the COVID-19 Pandemic in accordance with the Government guidance framework “Working Safely during COVID-19 in Construction and Other Outdoor Work.” This ensured best practice procedures for safety and social distancing were trouble-free protecting the health and wellbeing of workers.

All work was delivered in accordance with IGE/TD/1 Edition 5 and NG specifications T/SP/PW/11 Parts 1 & 2 and T/SP/SSW/22.

Project Management:

  1. Dedicated Project Management team established consisting of key REL staff.
  2. Planning, management & implementation of project controls including: Construction Programme, Quality Assurance, Environmental and Health & Safety Management, HAZONs, phased RAMS submissions, weld procedure approvals, welder qualifications, Temporary Works Design, utility/GPR surveys, procurement, emergency response, waste management, traffic management & security arrangements.
  3. Acted as Principal Contractor under CDM 2015, managing & coordinating all site construction activities throughout project lifecycle.
  4. Coordination & management of subcontractors, specialist suppliers & stakeholders ensured efficient, trouble-free project delivery.

Offsite Fabrication

To minimise on-site activities, REL fabricated pipework at its Ilkeston fabrication facility:

  1. Fabrication of MEC inlet & outlet header pipework, Pig Trap ‘C’ tie-in assemblies, 100mm (4″) drop leg pipework & associated support steelwork into transportable sections.
  2. Fabrication of adjustable pipe support assemblies for installation within the MEC compound.
  3. Inspection, Non-Destructive Testing (NDT) by Phased Array, hydrostatic testing, coating & painting of fabricated pipework.
  4. Pipework cleaned internally, sealed & transported to site utilising the REL in-house haulage capability.
Stringing 100mm Connecting Pipework
Excavating Open Cut Trenches
Installation of Ditched Pipework Sections

Construction Works:

  1. Completed Surveys (GPS & Utilities), trial holes & site setting out.
  2. Provision & setup of temporary site facilities for welfare, REL/NG offices, bunded fuel bowser, storage, & signage.
  3. Topsoil stripped & security fencing installed for compound / works area.
  4. Constructed reinforced concrete bases for control room, satellite equipment, two pressure transmitters, six 100mm pipe supports & associated road / crossing points.
  1. Constructed reinforced concrete foundation & completed in-situ concrete upstands for isolation joint IJ001.
  2. Excavated & installed duct routes & associated draw pits, with E&I installation undertaken by others.
  3. Constructed open-cut crossings for pipework & duct installations within terminal.
Installing Inlet Pipework to AG Valve Skid
Construction of Open Cut Road Crossing
Installing Outlet Pipework to Tie-in Point

Pipework Installation:

  1. Delivered & installed prefabricated below-ground inlet & outlet pipework, above-ground MEC header pipework & bridle connection pipework.
  2. Excavated separate inlet & outlet pipework trenches & installed temporary supports.
  3. Existing Feeder 17 Pig Trap ‘C’ pipework isolated & made safe to facilitate connection works.
  4. Installed interconnecting 100mm inlet & outlet pipework spools.
  5. Installed MEC inlet & outlet header pipework connecting Feeder 17 Pig Trap ‘C’, new MEC facility & AE customer tie-in point.
  6. Installed isolation joints & associated support structures.
  7. All welding completed in accordance with T/SP/P8 & T/SP/P2 specifications.
  1. Installed adjustable pipe supports (6 x 100mm, 4 x 200mm) & associated support steelwork.
  2. Tied into the existing 200mm (8”) Feeder 17 Pig Trap ‘C’ bridle pipework via a 200 x 200 x 100mm reducing tee with a 100mm branch connection.
  3. Installed two 200mm (8”) flanged plug valves & a ventable spool within Feeder 17 bridle pipework to provide a Double Block and Bleed (DBB) facility.
  4. Installed outlet pipework to customer tie-in location for final connection by AE.
  5. Completed bedding, pipe surround & backfilling of below-ground pipework. All earthworks undertaken in accordance with T/SP/CE/1.
Installing MEC Inlet & Outlet Header Pipework
Connecting 100mm Below Ground Pipework
Installing Below Ground Pipework at AG Skid

Cathodic Protection:

  1. Supplied & installed sacrificial-anode cathodic protection system, associated CP connections & cabling, test & marker posts.
  2. Completed CP commissioning, including DCVG & CIPS surveys for new pipework installation.
Blasting & Coating Pipework
Installing Sacrificial Anode CPS
Hydrostatic Testing of MEC Pipework to 112.5 Bar

Testing & Pre-commissioning:

  1. Completed 100% phased-array ultrasonic testing (PAUT) of applicable welds & associated inspection activities to T/SP/NDT/2.
  2. Completed hydrostatic testing to 112.5 bar, followed by draining & drying to -20°C dew point.
  3. All pipework coated & painted grey (BS 00 A 05).
  4. Completed required golden welds following successful hydrostatic testing.
  5. Completed & submitted RE18 documentation to National Grid, enabling review & production of commissioning certification.
  6. Provided assistance during final client commissioning activities.

Completion & Reinstatement:

  1. Reinstated concrete & tarmac surfaces at three road pipe & duct crossings.
  2. Constructed a new concrete footpath.
  3. Installed edgings around MEC area & laid terram geotextile membrane & stone chippings.
  4. Reinstalled fencing & site kirbing following completion of the works.
  5. Reinstated disturbed areas, including seeding & restoration of temporary compound & laydown areas.
  6. Removed cabins, cleared laydown area & demobilised from site.

Completed Feeder 17 Pig Trap ‘C’ tie-in comprising of new 100mm branch connection, double block and bleed (DBB) facility, below-ground interconnecting pipework & final landscaping.

OUTCOME

The project was successfully delivered in full compliance with the programme specification, without any complications. All works were completed on schedule, within budget and in strict accordance with the approved design and RAMS, ensuring full adherence to CDM 2015 duties.

REL provided full handover documentation including As-Built drawings, welding and fabrication records, inspection and pressure test certification, commissioning documentation, the Health & Safety File and project Data Books, supporting National Grid asset acceptance, commissioning and final project handover.

The completed MEC enabled the direct delivery of processed gas from the Saltfleetby Gas Field into National Grid’s Feeder 17 pipeline, providing Angus Energy with a new export route to the National Transmission System.

Completed Twin Stream MEC Valve Skid, associated above & below-ground pipework, new foundations, access paths & final landscaping.