BACKGROUND
Gas distribution company, Southern Gas Networks (SGN) needed to modernise their ageing gas infrastructure serving the Isle of Wight (IoW) because it had reached the end of its lifecycle. Originally installed post war, the existing supply was over 40 years old and showing signs of degradation.
Gas supply consisted of three old High Pressure (HP) Pipelines running across the Western Solent seabed floor, a distance of around 2.5kms. These ran from Lepe, in the New Forest, Hampshire on the UK mainland to a Pressure Reduction Station (PRS) at Egypt Point on the IoW, supplying around 56,000 people on the island.
The old Pipelines needed replacing due to ground instability issues and increased vulnerability from scour on the seabed floor. The PRS also needed to be relocated to a more stable location to maintain integrity and security of gas supply.
A major marine and onshore engineering project was initiated to replace the old Cross Solent Pipelines and to upgrade the gas infrastructure on the IoW. The project cost over £21m in total, took four years planning, and involved a world record drilling operation underneath the Solent seabed.
Marine works required the replacement of all three existing undersea HP Gas Pipelines. Two new 300mm (12”) Steel Gas Pipelines were installed running from Lepe, on the mainland, crossing the Solent to a new PRS at Gurnard on the IoW.
The Horizontal Directional Drilling (HDD) technique was used to run the new Pipelines underneath the seabed to a depth of 63m. At 3,926m (12,880 ft) and 3,930m (12,894 ft) respectively. These were believed to be the two longest Pipelines installed by HDD in the world at the time.
WATCH SGN VIDEO OF PROJECT
Watch the SGN video showcasing the Cross-Solent Pipeline Replacement project, which included what was believed to be the world’s longest HDD-installed gas pipelines at the time, together with the Rayden Engineering Limited (REL) onshore infrastructure works on the IoW.
ABOUT SGN

Previously known as Scotia Gas Networks until 2014, SGN is one of four local gas distribution operators in the UK.
The company manages a network of 71,000 kms of underground pipelines that deliver natural and green gas to around six million homes and businesses across Scotland, Southern England, and part of Northern Ireland.

SCOPE
SGN commissioned Rayden Engineering Ltd (REL) to complete all onshore works, while marine operations (for new Cross Solent Pipelines) were carried out by other contractors.
Project scope included design of temporary works, supply of materials (other than free issue), fabrication, installation, and construction of:
Scope included:
- New HP to Intermittent Pressure (IP) PRS at Gurnard, IoW.
- New 600mm (24”) Cross-Country HP Pipeline between new PRS & existing infrastructure at Tuttons Hill, IoW – approximately 1.5km.
- Link new Cross Solent Pipelines back to existing valve installation at Lepe, UK mainland.
- New Pig Trap installation & link to new Solent Pipeline on IoW (Gurnard AGI).
- Decommission & dismantle existing Solent Pipelines & PRS at Egypt Point.
- Construct new Pig Traps for new Solent Pipeline at Lepe, UK mainland.



SERVICES DELIVERED
REL served as Principal Contractor under CDM 2015, starting works in November 2010 and completing them within 14 months. All work was completed in accordance with SGN and other relevant specifications, standards, and procedures, as required for successful project delivery.
Due to the IoW’s heavy reliance on tourism, works were scheduled during the off-peak season to avoid disruption to visitors and events.
The new onshore Gas Pipeline’s route traversed landowner’s gardens and a busy road critical for tourist travel during summer. This necessitated meticulous planning and management of the project to minimise community disruption.
Additionally, the IoW’s National Landscape is a designated Area of Outstanding Natural Beauty (AONB), demanding REL’s adherence to required legislation and best practices to safeguard the environment.
The IoW is a vital habitat to the endangered British Red Squirrel. This required mitigation measures to be taken during construction to protect their welfare and habitat, such as acoustic barriers and light restrictions.
Project Management:
A dedicated Project Management team was setup with key REL staff for detailed planning & management throughout the Project lifecycle with:
- Development, management & operation of: Construction Programme, Risk Assessments & Method Statements (RAMS), Weld Procedure Specifications, Temporary Works (TW), Quality Assurance, Environmental, Health & Safety, Emergency Response, Traffic Management & Security Plans.
New HP to IP PRS at Gurnard, IoW:
Construction and installation of a new permanent PRS compound at Rew Street, Gurnard with above and below ground pipework, three single storey prefabricated buildings and associated equipment. All mechanical and civil works:
- Topsoil strip, cut & fill, grade PRS & AGI areas.
- Installation of temporary & permanent drainage system.
- Construction of concrete bases & foundations for buildings & equipment.
- Installation of new Filter, Heat Exchanger, Regulator Streams, Boiler House & Boiler Supply skids.
- Fabrication & installation of all pipework for site inlet, intermediary & outlet pipework, water & gas feeds to boilers & relief & vent pipework on Heat Exchanger.
- Excavation of trenches & bell holes for interconnecting pipework & welding.
- Lower & lay, weld & connect below ground pipework.
- Radiography testing (to T/SP/P2 & T/SP/NDT/2), inspection & coating all new pipework & equipment (to T/SP/CW/5).
- Installation of Regulator Housing & Instrumentation Kiosk.
- Hydrostatic & pneumatic testing & drying to -20oc for new installation – AGI to Pig Traps (to IGE/TD/1 , T/PR/PT/1 & IGE/TD/13).
- Tie-in 600mm pipe at PRS outlet.
- Supply & installation of electrical & instrumentation duct work.
- Construction of access road, bollards, footpaths & hard standing areas.
- Supply & installation of security fencing & access gates.
- Reinstatement – replanting with native shrubs & trees.
- Assisted SGN commissioning new PRS & Boiler Plant.
New Pig Trap Installation & Connection to Cross Solent Pipelines, Gurnard, IoW
All mechanical and civil works:
- Cut & fill Pig Trap area.
- Supply & installation of concrete bases & foundations.
- Hand excavation of pipe ends from Solent Crossing.
- Fabrication & installation of new 300mm pipework to link from Solent Crossing to new PRS.
- Fabrication & installation of 450mm pipework up to the Pig Trap IV.
- Inspection, coating & testing.
- Excavation of trenches for interconnecting pipework – Pig Trap to Solent Pipelines & AGI Filters.
- Lower & lay, weld pipework, radiography testing (to T/SP/P2 & T/SP/NDT/2).
- Grit blast & epoxy coat pipework (to T/SP/CW/5).
- Construction of underground supports.
- Pipe bed, surround & backfill (to T/SP/P/10).
- Hydrostatic & pneumatic testing & drying to -20oc (to IGE/TD/1 , T/PR/PT/1 & IGE/TD/13).
- Final connections to new transits & IP Pipeline.
- Supply & installation of access roads, footpaths, bollards & hard standing.
- Supply & installation of all security fencing & access gates.
- Reinstatement – replanting with native shrubs & trees.



New Cross Country Pipeline, Gurnard to Tuttons Hill, IoW
Fabrication, construction & installation of new 600mm (24”) Cross Country HP Gas Pipeline running ∼1.5km from outlet of new PRS at Gurnard to existing IP Pipelines at Tuttons Hill.
The first section of the new pipeline (from new PRS at Gurnard) was installed using the HDD technique running underneath Rew St & Gurnard Luck Valley, an area of Special Scientific Interest (SSI), the remainder was by ‘Open Cut’.
Works included:
- Topsoil stripped for Pipeline route & drill area.
- Weld 600mm Steel Pipeline string for HDD crossing, was a triple string due to lack of working space.
- Radiography (to T/SP/P2 & T/SP/NDT/2), joint coating (to T/SP/CW/5) & Pressure Testing (to IGE/TD/13) of HDD pipe string.
- HDD drilling 870m beneath Rew St & Gurnard Luck.
- Pipe pullback through HDD bore hole on guide rollers with pulling head.
- String, Weld & 100% radiography testing (to T/SP/P2 & T/SP/NDT/2) of mainline pipework.
- Excavation of ‘Open Cut’ trenching, lower & lay Pipework.
- Tie-In pipework at connecting ends from HDD & both sides of Cockelton Lane.
- Pipe bed, surround & backfill (to T/SP/P/10).
- Completion of three Hot Taps (to T/SP/P9) onto existing 200mm, 250mm & 300mm IP Pipelines at Tuttons Hill Regulator site.
- Open Cut crossing of Cockleton Lane.
- Fabrication & testing pipework at Tutton Hill Regulator for end of line connection.
- Installation of all pipework connections to Hot Tap Valves.
- Tie-in new Pipeline at Tutton Hill.
- Pressure test & dry Pipeline (to IGE/TD/13).
- Assist Pipeline commissioning.
- Installation of CP system & marker posts.
- Installation of new security fencing, access gates & surface finishing Hot Tap Tees & main Regulator compounds.
- Box fencing & planting of native hedgerow.
New Connection to Cross Solent Pipelines on UK Mainland at Lepe
Fabrication and installation of new pipework to link between drilled sections and Lepe site including all inspection, coating, testing & reinstatement.
- Location of pipe ends from Solent Crossings & extend pipework to valve compound.
- Fabrication, radiography testing (to T/SP/P2 & T/SP/NDT/2), paint & coat all pipework & equipment (to T/SP/CW/5).
- Excavation of trenches for new 300mm pipework (from Solent line to Valve arrangement to temporary Pig Traps).
- Lower & lay, weld below ground pipework, radiography testing (to T/SP/P2 & T/SP/NDT/2).
- Grit blast & epoxy coat pipework (to T/SP/CW/5).
- Pipe bed, surround & backfill (to T/SP/P/10).
- Hydrostatic & pneumatic testing & drying to -20oc (to IGE/TD/1 , T/PR/PT/1 & IGE/TD/13).
- Tie-in new 300mm Pipeline.
- Assist with commissioning.
- Final reinstatement.

Connecting Cross Solent Pipelines at Gurnard



Decommission Existing Cross Solent Pipelines, PRS & IP Pipeline at Egypt Point, IOW
Following the successful commissioning of the new Solent Transit Pipelines, the new PRS, and cross-country supply there was a proving period of eight weeks, before any decommissioning work.
- Isolation of old Pipelines at Valve House.
- De-pressurised & purged new Pipelines & PRS with Nitrogen, then Air.
- Valves at Cow Lane, IoW closed, three IP Pipelines vented to atmosphere & purged with Nitrogen.
- Pipework severed by cold cutting & blanked at valves.
- Existing Solent Pipelines severed & flooded at low water line (UK Mainland & IoW).
- Above ground pipework at Egypt Point PRS cut back & removed.
- Valves, regulators & other equipment dismantled & transported to SGN site.
- All old buildings demolished to slab level.
- All surplus removed & disposed of.
- Stopple & cap off old IP Pipelines north of Tuttons Hill.
- Excavation, wrapping removal, installation of stopple fittings.
- Weld on Tees, drill stopple off, cold cut & weld on cap ends.
- Coating (to T/SP/CW/5), backfill (to T/SP/P/10) & reinstatement.
Decommissioning Redundant Pipework & Construction of New Pig Traps at Lepe, UK Mainland
- Cut back & removed all old above ground pipework.
- Valves, regulators & other equipment dismantled & transported to SGN site.
- Demolished old building & removed all material from site.
- Construction of concrete bases & foundations.
- Fabrication & installation of new pipework (from valves outside site up to Pig Traps & Bridle Line IV).
- Excavation of trenching, lower & lay.
- Welding & Radiography testing (to T/SP/P2 & T/SP/NDT/2).
- Grit blast & coating pipework with epoxy (to T/SP/CW/5).
- Construction of bases & installation of underground pipe supports.
- Pipe bed, surround & backfill (to T/SP/P/10).
- Hydrostatic & pneumatic testing & drying to -20oc for new installation (to IGE/TD/1, T/PR/PT/1 & IGE/TD/13).
- Supply & installation of access roads, footpaths, bollards, hard standing & all surface finishes.



OUTCOME
The project was successfully delivered in line with the approved designs and schedule, without encountering major issues. All tasks were completed within the allocated time frame, budget, and adhered to required specifications and standards. This project has ensured the continued provision of a safe and reliable gas supply to the IoW’s 56,000 plus customers for many years to come.
We collaborated very closely with SGN throughout this critical national project through regular meetings and discussions. This fostered an environment of openness, honesty, and trust which facilitated the project’s smooth delivery. We fulfilled all obligations under CDM 2015 and provided comprehensive handover upon completion.